Detours
Cameron County
Centre County
Clearfield County
Clinton County
Juniata County
McKean County
Mifflin County
Potter County
- Scope: Bridge replacement and miscellaneous construction
- Construction Timeframe: 4/15/2024 to 10/24/2024
- Traffic Control: Detour
- Detour length: 12 miles
- Detour implementation Date: 5/6/2024
- Anticipated Date Detour to be Lifted: 10/24/2024
- Contractor: Francis J. Palo, Inc.
- Current Contract: $1,177,019
View the SR 2019/A02 Project Detour Map (PDF)
- Scope:
- Construction Timeframe: 5/28/2024 to 7/19/2024
- Traffic Control: Detour
- Detour length: 5.8
- Detour implementatoin Date: 5/28/2024
- Anticipated Date Detour to be Lifted: 7/19/2024
- Contractor: PennDOT Juniata County Maintenance
- Current Contract: Not applicable
- Scope: Superstructure replacement and miscellaneous construction
- Construction Timeframe: 4/8/2024 to 7/8/2024
- Traffic Control: Detour
- Detour Length: Nine miles
- Detour Implementation: 4/8/2024
- Anticipated Date Detour to be Lifted: 7/8/2024
- Contractor: Glenn O. Hawbaker, Inc.
- Current Contract: $2,386,386
- Scope: Bridge removal/replacement, paving, utility relocation, guide rail, pavement marking
- Construction Timeframe: 4/1/2024 to 8/13/2024
- Traffic Control: Detour
- Detour Lenght: Less than one mile
- Detour Implementation Date: 4/1/2024
- Anticipated Date Detour to be Lifted: 10/18/2024
- Contractor: Nestlerode Contracting Company, Inc.